The project pilot plant is about to be operative

Project update

One of the main SINGLE project objectives is to validate the performance of our newly developed PCER stacks through a pilot plant setting. The core purpose of this phase is to ensure that these stacks operate efficiently and safely under their intended working conditions.

This month, we have successfully completed a Hazard and Operability (HAZOP) study to assess the safety of the pilot plant’s design. The insights and recommendations from this study have been thoroughly reviewed and integrated into the design. With these updates, the pilot plant design is now entering its finalization phase.

Looking ahead, we are on track for the construction phase to commence in September, in order to be fully operational by the very beginning of 2025. This milestone marks a significant step towards achieving our project goals and advancing the development of our stacks.